6 | \begin{objectif} |
---|
7 | This task relies to the diffusion of the project results. |
---|
8 | The objective is to ensure the COACH dissemination by publishing on a public WEB site all |
---|
9 | the information that a COACH user requires. |
---|
10 | The main information features are: |
---|
11 | \begin{itemize} |
---|
12 | \item The COACH releases (milestones and final release) and their associated installation manuals. |
---|
13 | \item The COACH user reference manual. |
---|
14 | \item The user manual of the various tools. |
---|
15 | \item A COACH tutorial. |
---|
16 | \item The conference publication. |
---|
17 | \item A user wiki. |
---|
18 | \end{itemize} |
---|
19 | \end{objectif} |
---|
20 | % |
---|
21 | \begin{workpackage} |
---|
22 | \subtask This \ST relies to the management of the WEB site and to the distribution of |
---|
23 | the COACH releases. |
---|
24 | \begin{livrable} |
---|
25 | \itemV{0}{6}{d}{\Supmc}{dissemination WEB site} |
---|
26 | This deliverable consists firstly in providing a WEB site (name, HTTP server |
---|
27 | setup, wiki) and secondly in defining the site map and finally in writting and |
---|
28 | installing the pages. |
---|
29 | \itemL{6}{36}{d}{\Supmc}{dissemination WEB site}{1:.5:.5} |
---|
30 | This deliverable corresponds to the standard management of a WEB site (modifying, |
---|
31 | adding, suppressing, replacing pages). |
---|
32 | Especialy the user reference manuals provided in the other tasks will be published |
---|
33 | on this site. The published articles will be also be installed in this site. |
---|
34 | \itemL{6}{36}{d+x}{\Supmc}{release handling}{1:.5:.5} |
---|
35 | This deliverable deals with the elaboration of the COACH software milestones and |
---|
36 | final releases with their installation manuals and to publish then into the WEB |
---|
37 | site. |
---|
38 | \CoutHorsD{12}{36}{\Stima}{dissemination}{0:2:2} |
---|
39 | \end{livrable} |
---|
40 | \subtask |
---|
41 | \label{subtask-tutorial} |
---|
42 | This \ST consists of making a COACH tutorial and to publish it on the public WEB |
---|
43 | site. The tutorial example will also be used as reference demonstrator of the |
---|
44 | framework. |
---|
45 | The application of this tutorial will be a Motion JPEG application. |
---|
46 | \begin{livrable} |
---|
47 | \itemV{0}{6}{x}{\Supmc}{tutorial specification} |
---|
48 | Choice of the application and its implementation as a C/C++ program. |
---|
49 | \itemV{6}{12}{d+x}{\Supmc}{tutorial} |
---|
50 | The application is split into two communicating parts, the PC part and FPGA-SoC part. |
---|
51 | Using the features the T0+12 milestone provides, |
---|
52 | the tutorial describes how this efficient partionning was obtained. |
---|
53 | The FPGA-SoC part is described as communicating task graph. The tutorial also describes |
---|
54 | how a promising task graph can be obtained. |
---|
55 | \itemV{18}{24}{d}{\Supmc}{tutorial} |
---|
56 | % \mustbecompleted{FIXME: LIP6 :: Avons (UBS) change le lead du livrable OK ?} |
---|
57 | % \mustbecompleted{FIXME: LIP6 :: C'est pas possible, car il faut changer aussi |
---|
58 | % au-dessus c'est le meme livrable en 3 fois. De plus la c'est plus une DOC CSG que HAS.} |
---|
59 | This tutorial shows how a task can be migrated to coprocessor using HAS tools and |
---|
60 | how FPGA-SoC can be generated and run to FPGA. This for HAS tools and and |
---|
61 | architectural template available in T0+24 milestone. |
---|
62 | \itemL{30}{36}{d}{\Supmc}{tutorial}{2:1:1} |
---|
63 | The final release of the tutorial. |
---|
64 | \itemL{30}{33}{d}{\Sxilinx}{optimisation for \ganttlf \xilinx RTL tools (6)}{0:0:0.5} |
---|
65 | \xilinx will check that developped tutorial works well with \xilinx tools, |
---|
66 | and will propose corrections or enhancements if needed into a document. |
---|
67 | \end{livrable} |
---|