Ignore:
Timestamp:
Jan 24, 2011, 1:17:23 PM (13 years ago)
Author:
coach
Message:

TIMA : update de notre section ressource

File:
1 edited

Legend:

Unmodified
Added
Removed
  • anr/section-ressources.tex

    r320 r325  
    109109  No specific equipment acquisition.
    110110\item [Personnel costs]
    111   The permanent personnels involved in the project are professor and assistant professor
     111  The permanent personnels involved in the project are professor and associate professor
    112112  (Fr\'ed\'eric P\'etrot and Olivier Muller).
    113113  The non permanent personnels are Phd students and post-doc researchers.
    114114  Related costs are estimated in \hommemois.
    115   One phd student (Adrien Prost-Boucle), funded by the french ministry of research, will
     115  One phd student (Adrien Prost-Boucle), funded by the French ministry of research, will
    116116  be working on the project.
    117   One 100\% funded phd student will be hired in september 2010. A post-doc researcher will
    118   be hired at the end of 2011 for one year and an half.
     117  One 100\% funded phd student will be hired in September 2011. A post-doc researcher will
     118  be hired at the end of 2012 for one year.
    119119  The PhD student will mainly work on the evolution of UGH HLS tool. Thus, we are looking
    120120  for a profile with strong informatic skills and good knowledge in computer architecture.
    121   The post-doc will mainly work on FPGA reconfiguration and HPC. The required profile
     121  The post-doc will mainly work on HPC. The required profile
    122122  will be more oriented on computer architecture and advanced digital design.
    123123  \parlf
    124   The table below sumarizes the man power in \hommemois by tasks for both permanent and
     124  The table below summarizes the man power in \hommemois by tasks for both permanent and
    125125  non-permanent personnels. The detail by deliverables is given in
    126126  figure~\ref{table-livrables-1}.
    127   The requested funding for personnels represent 50\% of the total personnal costs.
    128   The requested funding for non permanent personnels is 85\% of the total ANR requested
     127  The effort of permanent personnels represents 50\% of the total effort.
     128  The requested funding for non permanent personnels is 86\% of the total ANR requested
    129129  funding.
    130130    \begin{center}\input{table_tima_short.tex}\end{center}
     
    133133\item [Travel]
    134134  The travel costs are associated to project meeting as well as participation to
    135   conferences. The travel costs are estimated to 11\% of the total requested ANR funding.
     135  conferences. The travel costs are estimated to 10\% of the total requested ANR funding.
    136136\item [Expenses for inward billing]
    137137  The costs justified by internal invoicing procedures are evaluated to 4\% of the total
Note: See TracChangeset for help on using the changeset viewer.